【6】Construction Supervision For The Mae Chan Community Flood Protection System Project, Phase 3, Mae Chan District, Chiang Rai Province. (MC3 6903CS)

【6】Construction Supervision For The Mae Chan Community Flood Protection System Project, Phase 3, Mae Chan District, Chiang Rai Province. (MC3 6903CS)

  • Location :

    Mae Chan District, Chiang Rai Province.

  • General Information :

    Includes Construction Of Flood Protection Embankments, Drainage Channels, Drainage Pipes, And Drainage Structures; Machinery And Equipment Works; And Other Works, Namely: 1. Construction Of Mae Chan Canal Flood Protection Embankment (FP1) Construction Of Flood Protection Embankment Type 4A (FP1), Left Bank, Section 1 From Km 0+043.00 To Km 0+350.00 (307.00 M); Construction Of Flood Protection Embankment Type 4A (FP1), Right Bank, Section 1 From Km 0+043.00 To Km 0+350.00 (307.00 M); Construction Of Flood Protection Embankment Type 4A (FP1), Left Bank, Section 2 From Km 0+370.50 To Km 0+656.00 (285.50 M); Construction Of Flood Protection Embankment Type 4A (FP1), Right Bank, Section 2 From Km 0+370.50 To Km 0+656.00 (285.50 M); Construction Of Flood Protection Embankment Type 4 (FP1), Left Bank, Section 3 From Km 0+676.50 To Km 1+400.00 (723.50 M); Construction Of Flood Protection Embankment Type 4 (FP1), Right Bank, Section 3 From Km 0+676.50 To Km 1+400.00 (723.50 M); Construction Of Flood Protection Embankment Type 4 (FP1), Left Bank, Section 4 From Km 1+420.50 To Km 1+656.00 (235.50 M); And Construction Of Flood Protection Embankment Type 4 (FP1) Right Bank, Section 4, From Km 1+420.50 To Km 1+656.00, 235.50 M. 2. Drainage System Construction. Construction Of Drainage Channels. Construction Work Is Underway On The Following Drainage Pipes: A Roadside Drainage Ditch (DR1) From Km 0+000.00 To Km 0+318.00 (318.00 M), A Drainage Pipe In Soi Hirannakorn 11 (DR2) From Km 0+000.00 To Km 0+225.00 (225.00 M), A Drainage Pipe In Soi Ruam Phatthana 1/2 (DR3) From Km 0+000.00 To Km 0+163.00 (163.00 M), And A Drainage Pipe In Soi Ruam Phatthana 1/2 (DR4) From Km 0+000.00 To Km 0+149.00 (149.00 M). And Drainage Pipeline Construction, Soi Behind Nuanchan Market (DR5), From Km. 0+000.00 To Km. 0+100.00 (100.00 M) 3. Drainage Structure Construction Reinforced Concrete Weir (Locations 1, 2, And 3) And Reinforced Concrete Sluice Gate 4. Machinery And Equipment Mobile Water Pumps (Capacity 0.25 M³/Sec, 6 Units), Including Accessories And Towing Vehicles

  • Construction Cost :

    298.50 Million Baht

  • Owner :

    Department of Public Works and Town & Country Planning

  • Design by :

    Department of Public Works and Town & Country Planning

  • Construction by :

    S. Sirichai Co., Ltd.

  • Completion Date: :

    16 August 2028